Skip to main content

Commissioning Management

Commissionability Review

Review building services drawings and specifications to check that the systems can be safely tested, balanced and commissioned to meet the design intent.

Check that the design provides suitable access to equipment, test points, balancing devices and isolation valves.

Review controls sequences and interfaces between building services to confirm that normal operation, alarms and failure responses can be verified.

Raise commissioning issues with the design team early so they can be resolved before installation.

Commissioning Plan/ Commissioning Programmes

Produce a commissioning plan with the assistance of the main contractor and specialist sub contractors to describe how the commissioning work will be undertaken.

This will include pre-requisites, interfaces, required information, standards applied, commissioning procedure and test sheets to be used.

Provide a coordinted commissioning plan showing duriations and logical pathways to achieve commissioning completion.

Commissioning Tracking Document

A comprehensive data base of the equipment to be commissioned will be produced.

This will be used to track the various commissioning activities for each item or system, such as installation complete, pre-commissioning, commissioning, test documentation and acceptance status.

The tracking document is a simple but powerful tool to easily identify the status of the commissioning activities.

Regular updates will be provided as part of the commissioning report.

Site Observations

Attending site during the services installation period to check for commissionability, e.g. valves installed in the correct locations.

We will also comment on access for operations and maintenance.

Our observations will be recorded on the tracking documents.

Note that this review does not replace the construction monitoring service required by the design team.

Witnessing of Commissioning

When a specialist contractor has completed a pre-commissioning or commissioning activity the associated test documentation will be submitted for review.

The commissioning manager shall check the documents for completeness and correctness (it is surprising how often incorrect data is used) and, if satisfied, arrange a witness demonstration.

Typically the commissioning manager shall witness a sample of the offered system to determine if the commissioning has been performed correctly.

If the results from the sample match the recorded values then the witness is generally considered to be successful.

If the outcome of the initial witness is not satisfactory then the sample size should be increased.

Should the demonstration continue to prove unsuccessful then it shall be marked as a failure.

The contractor shall need to re-commission and re-apply for a witness.

Sample sizes tend to be in the region 10-20% of the total system (e.g. if 200 valves are measured then a witness would typically be around 20-30).

This is not a fixed value and the most important outcome is that the commissioning manager has confidence the system has been correctly commissioned and the recorded results reflect the current status.

For some systems, such as life safety systems, we prefer to perform a 100% witness.

Client Training

This is a process that is seldom performed correctly and we consider it unforgiveable.

CxM can help manage the client training process so the operations team understand the building prior to handover.

We also push for draft O&M manuals to be made available as soon as possible to assist in this learning process.

Additional Services

As a commissioning manager we can provide a number of additional services which are often requested:

  • Fine tuning input
  • O&M Manual review for commissioning items
  • Defect Liability Period final inspection
  • Producing owner’s project requirements (OPR) and building user guides
  • Landlord/Tenant liaison for commissioning

If you can't find what you're looking for, get in touch to discuss.

CONTACT