Southern Cross Hospital
New Plymouth
2024
205 Saint Aubyn St, New Plymouth 4310
Project Details
205 Saint Aubyn St, New Plymouth 4310
Southern Cross Hospital
New Plymouth
Overview
During 2021 the Southern Cross Hospital in New Plymouth underwent a considerable upgrade An extension was constructed and stitched into the existing operational facility, adding two operating theatres, a Daystay ward and a PACU ward. New plant and plant spaces were provided to serve these new areas. Existing services, such as medical gases, were extended to serve the new spaces. The hospital remained operational throughout the project.
In 2024 and into 2025 additional upgrades were carried out throughout the hospital. This included work to existing HVAC systems, passive fire and active fire systems. Final integrated testing was completed in February 2025.
Our role
For the initial hospital expansion project we provided an ICA role to the hospital. Tasks included:
Design reviews for commissionability
Assisting the contractor to develop an integrated commissioning programme and commissioning plans
Witnessing tests on the HVAC systems
Reporting on commissioning activities to the client
Intensive testing and witnessing of the fire alarm system
For the upgrade works performed during 2024/25 we conducted thorough testing and witnessing of the fire alarm system. These tests were repeating several times following any significant modification to the system.